Sun 103

Project Type
Corporate Office, Sustainable

Location
Sunnyvale, CA

Project Size
320,000 sf

Architect
WRNS Studio

This 8-story tenant improvement comprises (4) stories of R&D lab spaces and (4) stories of office space. Operating as the design-build electrical contractor, this complex and challenging build consisted of a new 4000A service to support the (4) floors of labs, new distribution equipment, UPS, branch power, lighting, lighting controls and fire alarm. The density of MEP systems on the lab floors required extensive preconstruction and BIM coordination efforts to ensure construction progressed onsite to meet the schedule. A collaborative and adaptive approach to both design and construction by the architect, general contractor and MEP trade partners was vital to the success of this project particularly during the height of the COVID-19 pandemic.